This job began as a copper roof and gusset (flat section of roof between slopes) restoration.
Once work began, we discovered that the stucco on the wall above was also leaking. This long-term deterioration of the leaking stucco wall led to a void and separation of the stucco veneer from the house framing and impending collapse. Owner decided to replace the stucco wall with James Hardie Cedarmill siding instead of stucco.
Scaffold was setup to safely remove the failed stucco. Once the stucco was removed, new copper step flashing and wall flashing was installed to properly join the tile roof to the wall.
New James Hardie Cedarmill siding was painted to match the house and installed with a custom Azek PVC freeze board, which these modern materials are used as they will not rot.
Once the siding was finished the double locked copper roof and flat seam copper gusset were completed.